I'm looking to install a 30' decking platform (for a yurt), 3' above grade, on a plot of land I own. The site has a mild grade (5-10%), made up of metasedimentary rock, with ~1" of organic matter at the surface (not enough to dig into). What footings or reinforcement strategy would you recommend for a site like this?
Asked
Active
Viewed 1,819 times
2 Answers
10
1" of organic matter on rock? remove all the organic matter from the locations where the footings go, pour concrete footings or piers on the rock surface directly. Might be a good idea to drill holes in the rock and grout in some rebar at each location to tie the pier or footing to the rock.
Ecnerwal
- 235,314
- 11
- 293
- 637
7
sedimentary rock can be quite soft / should be easy to drill. fine for compressive strength.
- drill 8" deep holes using rotary hammer 3/4" quad carbide bits
- blow out the holes / clean holes with hilti wire brush
- epoxy (HY150) 5/8" rebar into holes and have that extend up into your footing
- 8" diameter sonotube the footings to get yourself to the height you want for your platform
- put post anchor saddles into place on the sonotube to receive your beams or posts